Upcoming works

Advance notice – excavator delivery to site 

9 June 2021 

We are expecting a delivery of a 360o demolition excavator on Tuesday 15 June. It will arrive at 05:30 at Gate 1 on New Kent Road. Due to the size of the excavator, it will be delivered to site under a Metropolitan Police Movement Order. Whilst we’ll ensure best practicable means are implemented to minimise noise levels for our neighbours during the delivery, we do expect there to be some noise as it gets settled in.

Please accept our apologies in advance for any inconvenience caused by the delivery and thank you for bearing with us as we continue to make progress at pace on site.

Should you need to get in touch, our dedicated 24 hour contact number and email address is 07395 792 302 / elephantandcastle@keltbray.com

Advance notice – JuNE SCHEDULE OF NIGHT WORKS TO CARRY OUT ENABling WORKS AND SCAFFOLDING

Out of hours scaffold works on the Coronet Theatre and Shopping Centre South will continue to be carried out by Keltbray on the dates outlined below in June. Due to the immediate proximity of Network Rail’s railway line, these works have to take place during these times for safety reasons.

Our team will work to minimise noise where possible. All deliveries will be received during normal site working hours, and there will be no additional traffic or vehicle noise during these times.

Should you need to contact the site team, the dedicated 24 hour contact number is 07395 792 302.

Start End
Date Time Date Time
02/06/2021 00:01 02/06/2021 05:00
03/06/2021 00:01 03/06/2021 05:00
04/06/2021 00:01 04/06/2021 05:00
06/06/2021 01:45 06/06/2021 08:00
08/06/2021 00:10 08/06/2021 05:00
09/06/2021 00:10 09/06/2021 05:00
10/06/2021 00:10 10/06/2021 05:00
11/06/2021 00:10 11/06/2021 05:00
12/06/2021 01:00 14/06/2021 03:45
15/06/2021 00:01 15/06/2021 05:00
16/06/2021 00:01 16/06/2021 05:00
17/06/2021 00:01 17/06/2021 05:00
18/06/2021 00:01 18/06/2021 05:00
19/06/2021 00:01 19/06/2021 05:00
20/06/2021 01:45 20/06/2021 09:15
22/06/2021 00:01 22/06/2021 05:00
23/06/2021 00:01 23/06/2021 05:00
24/06/2021 00:01 24/06/2021 05:00
25/06/2021 00:01 25/06/2021 05:00
26/06/2021 00:01 26/06/2021 05:00
27/06/2021 03:40 27/06/2021 08:00
29/06/2021 00:01 29/06/2021 05:00
30/06/2021 00:01 30/06/2021 05:00

*Existing possession

Please note that shift patterns may change due to adverse weather conditions.

Latest newsletters

As part of our efforts to update and inform the local community, the project team shares a regular newsletter with our direct neighbours and subscribers. This newsletter provides the latest information on the works programme on site.

To sign-up to our digital mailing list, click here.

SEE BELOW For the latest version of the Community Update newsletter.

  • Issue 9

  • Issue 8

  • Issue 7

  • Issue 6

  • Issue 5

  • Issue 4

  • Issue 3

  • Issue 2

  • Issue 1

Neighbourhood Information Forums

In addition to our newsletters, we have also set up Neighbourhood Information Forums, which provide an opportunity to meet with members of the project team, discuss the works programme in more detail and ask any questions that you may have.

If you would like to attend the next Neighbourhood Information Forum and/or receive calendar notifications, please email info@elephantandcastletowncentre.co.uk to sign up.

View the latest Neighbourhood Information Forum recording below.

  • Neighbourhood Information Forum May 2021

  • Neighbourhood Information Forum April 2021

  • Neighbourhood Information Forum March 2021

  • Neighbourhood Information Forum February 2021

  • Neighbourhood Information Forum January 2021

  • Neighbourhood Information Forum December 2020

  • Neighbourhood Information Forum November 2020

  • Elephant & Castle Town Centre neighbourhood information

    Neighbourhood Information Forum October 2020

  • Neighbourhood Information Forum September 2020

Construction Phases

When the shopping centre closed on the 24th September the site was secured and Heras fencing was erected.

The access route through the shopping centre is now closed from the overground station and pedestrians are to follow the enhanced pavement route along Elephant Road for access between the Rail and Northern/Bakerloo Line Underground stations.

The deconstruction works will commence in October with the erection of a more substantial site hoarding. This hoarding will contain a number of dedicated vehicular access gates that will transition through 7 logistics phases during all works on site.

Click on each phase image to see a larger version.

  • PHASE 1

    PHASE 1: JULY 2020 - OCTOBER 2020

  • PHASE 2

    PHASE 2: AUTUMN 2020 - AUTUMN 2021

  • PHASE 3

    PHASE 3: AUTUMN 2021 - SUMMER 2022

  • PHASE 4

    PHASE 4: SUMMER 2022 - AUTUMN 2022

  • PHASE 5

    PHASE 5: WINTER 2022 - AUTUMN 2025

  • PHASE 6

    PHASE 6: AUTUMN 2024

  • PHASE 7

    PHASE 7: AUTUMN 2025

Job Opportunities

Both Keltbray and Multiplex are highly motivated and focused on providing local people with employment and upskilling. During the development, a number of opportunities will be created and these will include apprenticeships, new entrant positions, short courses and work experience placements. As well as supporting a variety of educational activities with local schools, colleges and universities.

Email info@elephantandcastletowncentre.co.uk for more information.

Keltbray logo