Upcoming works

Advance notice – Removal of Welfare Cabins on site

On Thursday 20 May, between 5.00am – 8.00am the temporary cabins on the South West corner of the Elephant and Castle Town Centre site (on the corner of Newington Butts and Walworth Road) will be removed from the site by lorry.

We will ensure that this activity is carried out promptly and we will minimise noise as much as possible as the cabins are loaded onto the lorries.

If you do need to contact the site team, the dedicated 24 Hour contact number is 07395 792 302.

Advance notice –MAY SCHEDULE OF NIGHT WORKS TO CARRY OUT ENABling WORKS AND SCAFFOLDING

Out of hours scaffold works on the Coronet Theatre and Shopping Centre South will continue to be carried out by Keltbray on the dates outlined below in May. Due to the immediate proximity of Network Rail’s railway line, these works have to take place during these times for safety reasons.

Our team will work to minimise noise where possible. All deliveries will be received during normal site working hours, and there will be no additional traffic or vehicle noise during these times.

Should you need to contact the site team, the dedicated 24 hour contact number is 07395 792 302.

Start End
Date Time Date Time
04/05/2021 00:10 04/05/2021 05:00
05/05/2021 00:10 05/05/2021 05:00
06/05/2021 00:10 06/05/2021 05:00
09/05/2021* 01:45 09/05/2021 08:00
11/05/2021 00:10 11/05/2021 05:00
12/05/2021 00:10 12/05/2021 05:00
13/05/2021 00:10 13/05/2021 05:00
16/05/2021* 01:45 16/05/2021 08:00
18/05/2021 00:10 18/05/2021 05:00
19/05/2021 00:10 19/05/2021 05:00
20/05/2021 00:10 20/05/2021 05:00
23/05/2021* 01:45 23/05/2021 08:00
25/05/2021 00:10 25/05/2021 05:00
26/05/2021 00:10 26/05/2021 05:00
27/05/2021 00:10 27/05/2021 05:00
30/05/2021* 01:45 30/05/2021 08:00

*Existing possession

Latest newsletters

As part of our efforts to update and inform the local community, the project team shares a regular newsletter with our direct neighbours and subscribers. This newsletter provides the latest information on the works programme on site.

To sign-up to our digital mailing list, click here.

SEE BELOW For the latest version of the Community Update newsletter.

  • Issue 8

  • Issue 7

  • Issue 6

  • Issue 5

  • Issue 4

  • Issue 3

  • Issue 2

  • Issue 1

Neighbourhood Information Forums

In addition to our newsletters, we have also set up Neighbourhood Information Forums, which provide an opportunity to meet with members of the project team, discuss the works programme in more detail and ask any questions that you may have.

If you would like to attend the next Neighbourhood Information Forum and/or receive calendar notifications, please email info@elephantandcastletowncentre.co.uk to sign up.

View the latest Neighbourhood Information Forum recording below.

  • Neighbourhood Information Forum April 2021

  • Neighbourhood Information Forum March 2021

  • Neighbourhood Information Forum February 2021

  • Neighbourhood Information Forum January 2021

  • Neighbourhood Information Forum December 2020

  • Neighbourhood Information Forum November 2020

  • Elephant & Castle Town Centre neighbourhood information

    Neighbourhood Information Forum October 2020

  • Neighbourhood Information Forum September 2020

Construction Phases

When the shopping centre closed on the 24th September the site was secured and Heras fencing was erected.

The access route through the shopping centre is now closed from the overground station and pedestrians are to follow the enhanced pavement route along Elephant Road for access between the Rail and Northern/Bakerloo Line Underground stations.

The deconstruction works will commence in October with the erection of a more substantial site hoarding. This hoarding will contain a number of dedicated vehicular access gates that will transition through 7 logistics phases during all works on site.

Click on each phase image to see a larger version.

  • PHASE 1

    PHASE 1: JULY 2020 - OCTOBER 2020

  • PHASE 2

    PHASE 2: AUTUMN 2020 - AUTUMN 2021

  • PHASE 3

    PHASE 3: AUTUMN 2021 - SUMMER 2022

  • PHASE 4

    PHASE 4: SUMMER 2022 - AUTUMN 2022

  • PHASE 5

    PHASE 5: WINTER 2022 - AUTUMN 2025

  • PHASE 6

    PHASE 6: AUTUMN 2024

  • PHASE 7

    PHASE 7: AUTUMN 2025

Job Opportunities

Both Keltbray and Multiplex are highly motivated and focused on providing local people with employment and upskilling. During the development, a number of opportunities will be created and these will include apprenticeships, new entrant positions, short courses and work experience placements. As well as supporting a variety of educational activities with local schools, colleges and universities.

Email info@elephantandcastletowncentre.co.uk for more information.

 

Keltbray logo