Advanced Notices

 

Notice of Early/Late start works

Our agreed working hours are currently as follows:

    • Monday to Friday – 08:00-20:00 (additional hours from 18:00-18:00) Acoustic blankets will be used for these back shift works where possible to help to further mitigate any noise disruption
    • Saturday – 08:00-16:00 (additional hours from 13:00-16:00) Acoustic blankets will be used for these back shift works where possible to help to further mitigate any noise disruption

The following activities have been planned for the months of August and September:

    • Saturday 3rd and Sunday 4th August – 08:00-16:00 Tower 3 screen removal
    • Saturday 10th and Sunday 11th August – 08:00-16:00 Tower 1 hoist climb
    • Saturday 17th and Sunday 18th August – 08:00-18:00 Tower 1 screen removal (08:00-16:00), Tower 1 hoist climb (08:00-16:00), Tower Crane 4 moves to Tower Crane 4a (08:00-18:00, can only be done on a weekend due to site safety)
    • Saturday 24th and Sunday 25th August – 08:00-16:00 Tower 1 screen removal and Tower 1 hoist climb
    • Monday 29th August to 13th September – 18:00-20:00 (Mon-Fri only) Bathroom pod deliveries
    • Saturday 14th and Sunday 15th December – 08:00-18:00 Tower Crane LUL dismantle (can only be undertaken on a weekend due to site safety and removal, this limits congestion on surrounding roads)

Notice of works to elephant road

Please be advised our supply chain partner, will be commencing works to connect the district heating to the new development. The first stage of the works will require hoarding lines to the West (outside of the station) and East (Castle Square) side of Elephant Road to be erected. The hoarding will be formed of ‘heras’ temporary fencing panels.

Throughout the excavation phase of works taking place outside the Elephant and Castle Train Station, a temporary traffic light system will be implemented on Elephant Road to ensure pedestrian safety. The road will remain accessible for vehicles and cyclists, though the road width will be restricted to accommodate the hoarding and works taking place. The road will remain open throughout the process.

 

Relevant signage will be in place to inform the passing public of the works, and diverting pedestrians through Castle Square, ultimately increasing footfall in this area. Discussions are taking place with the Developer to finalise signage and hoarding design. This programme of works will take place between Monday 17th July, commencing with the set up of the hoarding line, through to 2024.

Please note that these works will take place during normal working hours (08:00-18:00 Monday to Friday) and should any additional working hours be granted, we will ensure to update this website page.

EMployment/job opportunities

James Engineering – Site Labourer:

  • Role & Responsibilities – Assisting installation team with movement of materials around the project. Fire Watch / exclusion zone supervision. Filling and sanding of welded joints to prepare installed balustrade for site spraying. Fitting protection to finished areas of work.
  • Site start date – Imminently.

General Labourer:

  • Role & Responsibilities:  Maintaining clean working areas and supplying materials to roofers.
  • Site start date – June 2024

Throughout the lifecycle of the project we are targeting 73 new apprenticeship opportunities and 293 new entrant opportunities.

To register interest for any of these packages of works, please feel free to reach out to ECTC@multiplex.global


Throughout the lifecycle of the project we are targeting new apprenticeship opportunities and new entrant opportunities. We will have the following packages of work coming online over the next three years on site:

      • Louvres – May 2024
      • Kitchens – July 2024
      • WC and Shower Fit Out – April 2024
      • Decorations – November 2024
      • Floor Finishes incl. Tiling and Stone – June 2025
      • Raised Access Floors – January 2025
      • Signage – July 2024
      • Public Realm – February 2025
      • Cleaning – Ongoing

If you’d like to register your interest for any of these packages of works, please feel free to reach out to ECTC@multiplex.global

Latest newsletters

As part of our efforts to update and inform the local community, the project team shares a regular newsletter with our direct neighbours and subscribers. This newsletter provides the latest information on the works programme on site.

To sign-up to our digital mailing list, click here.

SEE BELOW For the latest version of the Community Update newsletter.

  • Issue 49

  • Issue 48

  • Issue 47

  • Issue 46

  • Issue 45

  • Issue 44

  • Issue 43

  • Issue 42

  • Issue 41

  • Issue 40

  • Issue 39

  • Issue 38

  • Issue 37

  • Issue 36

  • Issue 35

  • Issue 34

  • Issue 33

  • Issue 32

  • Issue 31

  • Issue 30

  • Issue 29

  • Issue 28

  • Issue 27

  • Issue 26

  • Issue 25

  • Issue 24

  • Issue 23

  • Issue 22

  • Issue 21

  • Issue 20

  • Issue 19

  • Issue 18

  • Issue 17

  • Issue 16

  • Issue 15

  • Issue 14

  • Issue 13

  • Issue 12

  • Issue 11

  • Issue 10

  • Issue 9

  • Issue 8

  • Issue 7

  • Issue 6

  • Issue 5

  • Issue 4

  • Issue 3

  • Issue 2

  • Issue 1

Neighbourhood Information Forums

In addition to our newsletters, we have also set up Neighbourhood Information Forums, which provide an opportunity to meet with members of the project team, discuss the works programme in more detail and ask any questions that you may have.

If you would like to attend the next Neighbourhood Information Forum and/or receive calendar notifications, please email info@elephantandcastletowncentre.co.uk to sign up.

View the latest Neighbourhood Information Forum recording below.

  • Neighbourhood Information Forum - June 2024

  • Neighbourhood Information Forum - April 2024

  • Neighbourhood Information Forum - February 2024

  • Neighbourhood Information Forum - December 2023

  • Neighbourhood Information Forum - November 2023

  • Neighbourhood Information Forum - October 2023

  • Neighbourhood Information Forum - September 2023

  • Neighbourhood Information Forum - August 2023

  • Neighbourhood Information Forum - July 2023

  • Neighbourhood Information Forum - June 2023

  • Neighbourhood Information Forum - May 2023

  • Neighbourhood Information Forum - April 2023

  • Neighbourhood Information Forum - March 2023

  • Neighbourhood Information Forum - February 2023

  • Neighbourhood Information Forum - January 2023

  • Neighbourhood Information Forum - December 2022

  • Neighbourhood Information Forum - November 2022

  • Neighbourhood Information Forum - October 2022

  • Neighbourhood Information Forum - September 2022

  • Neighbourhood Information Forum - August 2022

  • Neighbourhood Information Forum - July 2022

  • Neighbourhood Information Forum - June 2022

  • Neighbourhood Information Forum - May 2022

  • Neighbourhood Information Forum - April 2022

  • Neighbourhood Information Forum March 2022

  • Neighbourhood Information Forum February 2022

  • Neighbourhood Information Forum January 2022

  • Neighbourhood Information Forum November 2021

  • Neighbourhood Information Forum October 2021

  • Neighbourhood Information Forum September 2021

  • Neighbourhood Information Forum August 2021

  • Neighbourhood Information Forum July 2021

  • Neighbourhood Information Forum June 2021

  • Neighbourhood Information Forum May 2021

  • Neighbourhood Information Forum April 2021

  • Neighbourhood Information Forum March 2021

  • Neighbourhood Information Forum February 2021

  • Neighbourhood Information Forum January 2021

  • Neighbourhood Information Forum December 2020

  • Neighbourhood Information Forum November 2020

  • Elephant & Castle Town Centre neighbourhood information

    Neighbourhood Information Forum October 2020

  • Neighbourhood Information Forum September 2020

Construction Phases

Demolition works are now complete and Multiplex have taken possession of the site with the second phase targeted to be complete by 2026.

The access route through the site is closed from the overground station and pedestrians are to follow the enhanced pavement route along Elephant Road for access between the Rail and northern/Bakerloo Line Underground stations.

The first major construction works began in February 2022 with concrete piling ahead of building. Phase three will commence on the site of the London College of Communication after the College has moved to its new building within phase two.